Project Logistics

Yandin Wind Farm

PROJECT SCOPE:

  • Route Survey
  • Planning & Permit
  • Delivery
  • Storage & Offload

Delivering WA's biggest wind farm one monster component at a time

The Yandin Wind Farm consisted of 51 Vestas V150 4.2MW wind turbine generators, situated in Western Australia.
ARES transported all wind turbine components from the Port of Henderson south of Perth to site, a distance of 220km one way.

 

Keeping Pace Through Disruption

All 51 wind turbine generators were delivered to the Yandin site safely, on schedule and without a single stakeholder complaint, concluding 10 months of the most intensive wind transport program undertaken in Australia to date.

At peak, the combined Yandin and Warradarge operation delivered 5 complete turbines per week, a rate unmatched in the Australian market, while maintaining a faultless HSE record across the full program. The purpose-built nacelle jacking system removed the requirement for oversized craneage entirely, converting an engineering solution into a direct commercial benefit for the client. Yandin now operates as one of Western Australia’s largest wind farms, supplying clean energy to approximately 200,000 households, with every component delivered by ARES.

Project Challenges

  • 01

    Two mega-projects, one port

    Running Yandin and Warradarge simultaneously meant double the cargo, double the equipment and double the storage demands at Henderson. To keep pace, ARES deployed two brand-new 70T reach stackers, which are faster and more manoeuvrable than traditional cranes, to sustain an unprecedented run rate while still receiving cargo from incoming ships.

  • 02

    Record-breaking blades on tightly regulated roads

    At 73.6m, the V150 blades were the longest ever transported on Australian roads, and every individual component movement required a dedicated transport permit that could only be lodged 28 days ahead of the move. ARES developed the transport methodology in consultation with Main Roads WA, engineering a motorway routing that bypassed the Perth metropolitan area. Convoys of three departed at approximately midnight and arrived on site by sunrise, with permit sequencing and convoy scheduling managed in lockstep across hundreds of discrete movements.

  • 03

    Overweight nacelles

    The cargo manifest revealed a problem: each nacelle far outweighed every other component, which would normally force the use of an oversized (and expensive) crane at both port and site. ARES designed and fabricated a custom set of hydraulic jacks that lifted nacelles on and off trucks without a crane, saving Vestas significant site costs.

  • 04

    Bushfires, then a pandemic

    Major WA bushfires disrupted mobilisation, and the arrival of COVID-19 imposed strict constraints on rotating interstate crews. New protocols, permits and PPE were introduced without slowing the delivery schedule.

Cargo Carried

A breakdown of the specialised cargo transported as part of this project.

0
VESTAS WIND TURBINES

Each turbine stands 180m tall and produces 4.2MW, forming part of the largest wind farm in WA.

0
HEAVIEST COMPONENT

The Yandin nacelles were heavy weights and required a 96-wheel platform trailer to haul them.

0
BLADE LENGTH

That’s 10% longer than the wingspan of a Boeing 747 jumbo jet (68m).

0
TOTAL DELIVERIES

These include turbine components, towers, blades, transformers and containers.

51 WTGs were delivered safe and sound to the Yandin Wind Farm in WA by ARES, including the longest blade (73.6m) transported in WA.

Transportation in WA came with many challenges, including the fact that each component needed a permit and each permit could only be applied 28 days prior to transportation. Moreover, the bushfires added further difficulties during mobilisation. On top of that, COVID-19 caused many constraints regarding the rotation of interstate resources.

ARES managed to sail through all of these challenges successfully without complaints. ARES always came up with a solution when there was a problem, that made the job far easier than what it could have been otherwise.

RAJESH DUPURKAR, VESTAS PROJECT MANAGER, YANDIN WIND FARM